Feasibility Simulation Analysis of Close-Proximity Construction of
Underground Maglev Deep Foundation Pits Under Construction
Jingcheng Chen
1,* a
, Yiwen Yang
1
, Bo Zeng
2
, Bin Xie
2
, Siwei Liu
1
, Zhen Zhang
3
and Yang Zhong
4
1
China Construction Fifth Engineering Bureau Co., Ltd., Changsha 410004, Hunan, China
2
China Construction Fifth Engineering Bureau Third Construction Co., Ltd., Changsha 410114, Hunan, China
3
Hunan Sixth Engineering Co., Ltd., Changsha 410015, Hunan, China
4
Hunan Airport Management Group Co., Ltd., Changsha 410100, Hunan, China
*
Keywords: Geotechnical Engineering,·Numerical Analysis,·Deep Foundation Pit,·Close-Proximity Construction.
Abstract: To ensure the safety of deep excavations, construction is typically not allowed within a one-depth range
around the excavation. In the Changsha Airport Comprehensive Transportation Hub project, the proposed
West Parking Building is adjacent to an ongoing deep excavation for maglev construction, imposing
constraints. To optimize the schedule, a construction plan was devised for the West Parking Building near the
maglev deep excavation. Finite element analysis was employed to simulate the maglev deep excavation,
assessing displacements and mechanical changes in the soil and support structures under different scenarios.
The feasibility of the proximity construction plan was predicted, safety measures were proposed, and on-site
implementation validated the analysis accuracy. Results indicate that, under favorable geological conditions,
robust excavation support measures, and an appropriate proximity distance, the impact of proximity
construction on deep excavations is minimal, rendering the plan feasible. This research provides valuable
guidance for deep excavation construction.
1 INTRODUCTION
In recent years, the acceleration of urbanization and
advancements in construction engineering have led to
larger and more complex projects (
Ming 2023
). For
example, these projects face complex and variable
changes, such as groundwater levels and
heterogeneity of soil (
Vasilkin 2018
). While existing
research often qualitatively analyzes specific issues,
there is a lack of systematic, dynamic analysis of the
entire construction process (
Gao X et al. 2023
).
Against
this backdrop, ensuring the safety, efficiency, and
economic viability of construction plans has become
a pressing challenge in the field of geotechnical
engineering.
Feasibility analysis of project plans is a crucial
step in ensuring the efficient and safe completion of
projects. Consequently, numerous scholars have
conducted research in this area (
A I T, 2021; Zhan et al.
2021
). For instance, Yu Chunhong et al (
Yu et al. 2019
).
conducted a feasibility analysis of foundation pit
design schemes using anchor systems instead of steel
a
https://orcid.org/0009-0001-1432-3850
supports through theoretical calculations, addressing
the difficulties and extended timelines associated
with onsite steel support construction. Ma Linwei et
al (
Ma et al. 2022
). conducted research on the
feasibility of cross regional hydrogen water reverse
transportation system engineering based on the
approach of "scheme design and physical modeling
economic modeling of single agent operation
mode analysis of multi agent operation mode"; Cui
Guoyong et al (
Cui et al. 2022
). quantitatively
evaluated the feasibility of the new plan by analyzing
the advantages and disadvantages of using
TBM+main tunnel blasting method in terms of
construction period and cost through construction
organization design, including the plan of connecting
the horizontal guide, construction inclined shaft,
ventilation inclined shaft, and horizontal guide.
Scholars have extensively researched various projects,
employing different methods for feasibility analysis
(
Chen et al. 2020; Hua et al. 2020
). However, there is
scarce literature on the feasibility analysis of
Chen, J., Yang, Y., Zeng, B., Xie, B., Liu, S., Zhang, Z., Zhong and Y.
Feasibility Simulation Analysis of Close-Proximity Construction of Underground Maglev Deep Foundation Pits Under Construction.
DOI: 10.5220/0013636500004671
In Proceedings of the 7th International Conference on Environmental Science and Civil Engineering (ICESCE 2024), pages 271-278
ISBN: 978-989-758-764-1; ISSN: 3051-701X
Copyright © 2025 by Paper published under CC license (CC BY-NC-ND 4.0)
271
magnetic levitation deep foundation pit construction
using geotechnical engineering simulation software.
This paper uses geotechnical engineering
numerical analysis software to simulate and analyze
the feasibility of deployment plans for close-
proximity construction. The safety of optimized
schemes is validated through onsite implementation.
The goal is to uncover the significant potential of
geotechnical engineering numerical analysis in large
construction projects and provide insights for
improving construction management practices.
2 PROJECT STATUS
The Changsha Airport expansion project involves a
comprehensive transportation hub spanning 492,300
square meters. It comprises an underground facility
with four levels and five tracks, an aboveground
interchange hub, and associated municipal facilities
(see Figure 1). The complex network of deep
foundation pits (see Figure 2) features interconnected
excavations with varying elevations and shapes.
Ensuring safety and efficiency during the
construction phase of these foundation pits is pivotal
to the overall success of the project.
Figure 1: BIM model of structure.
Figure 2: BIM model of deep foundation pit group.
Due to safety concerns, the original plan requires
excavating the West Parking Building pit before
moving on to the magnetic levitation pit. This
sequence, waiting for the completion of the magnetic
levitation structure, significantly impacts the West
Parking Building construction schedule, posing
considerable timeline risks. Urgent optimization of
the West Parking Building pit design or adjustments
to the construction plan are needed to alleviate
schedule pressures (
Figure 3
).
Figure 3: Status of the construction site.
3 PLAN OF CLOSE-PROXIMITY
CONSTRUCTION
Given that both the magnetic levitation deep pit and
the West Parking Building are in moderately
weathered silty sandstone formations, and the West
Parking Building is situated beyond the rupture plane
of the magnetic levitation deep pit (horizontal angle
45°+φ/2 = 60°), an expedited construction proposal
has been introduced. The optimized plan suggests
commencing the construction of the West Parking
ICESCE 2024 - The International Conference on Environmental Science and Civil Engineering
272
Building structure in close proximity immediately
after completing the internal support structure
construction of the magnetic levitation deep pit. Due
to construction coordination uncertainties, the most
challenging scenario for this plan might occur when
the magnetic levitation deep pit is excavated to its
bottom while the West Parking Building reaches its
peak load (maximum load), as depicted in Figure 4.
Figure 4: Condition of section 33 of the west parking
building and maglev foundation pit of the original
construction scheme.
To ensure the safe and stable implementation of
the close-proximity construction plan for both the
magnetic levitation deep pit and the West Parking
Building, this study employs the finite element
method to conduct numerical simulations,
quantitatively analyzing the feasibility of the
proposed scheme.
4 NUMERICAL SIMULATION
AND RESULT ANALYSIS
4.1 Numerical Simulation Scheme
Using geotechnical finite element software, a 3D
numerical model was created to simulate and analyze
the safety of the magnetic levitation deep pit under
two scenarios: the original design and the close-
proximity construction plan. The aim is to assess the
feasibility of the close-proximity construction plan. A
3D finite element geometric model was established
for the adjacent area between the magnetic levitation
deep pit and the West Parking Building based on
construction drawings (see Figure 5).
In this area, the West Parking Building is divided
into West 21 Zone (light green), West 22 Zone (dark
green), and West 23 Zone (purple) moving from west
to east, close to the magnetic levitation deep pit. The
yellow marked area far from the magnetic levitation
deep pit is designated as West 1 Zone.
The analysis involves studying ground displacement,
deformation, stress distribution, and internal forces in
the surrounding structures under both scenarios.
Results will be compared with design specifications
to assess the impact of the West Parking Building's
close-proximity construction on the safety of the
magnetic levitation deep pit. The construction plan
considers the most adverse conditions and is
reasonably simplified, as outlined in Table 1.
Table 1: Construction
condition table.
Condition 1. The initial plan Condition 2. Close-proximity construction plan
Initial Stage: West Parking Building pit excavated to design
elevation; magnetic levitation deep pit excavated to the
bottom elevation of the crown beam, with installed
retaining piles, column piles, grid columns, crown beams,
and the initial concrete support.
Step 1: Construction of a 6level structure in West 1 Zone,
considering a 100 kPa load.
Step 2: Excavation of the magnetic levitation deep pit to
the bottom of the second support, with installation of steel
supports, steel girders, and connecting beams.
Step 3: Excavation of the magnetic levitation deep pit to
the bottom elevation without constructing the base slab.
Initial Stage: Same as Scheme 1 "Initial Stage."
Step 1: Same as Scheme 1 "Step 1."
Step 2: Construction of the structure in West 2
Zone, with West 21 and West 22 completing 6
levels considering a load of 100 kPa; West 23
Zone remains unconstructed, serving as a
temporary material storage area with a
temporary load of 20 kPa considered for the
most adverse conditions.
Step 3: Same as Scheme 1 "Step 2."
Step 4: Same as Scheme 1 "Step 3."
Feasibility Simulation Analysis of Close-Proximity Construction of Underground Maglev Deep Foundation Pits Under Construction
273
Figure 5: Formation geometry model.
4.2 Constitutive Model and Parameter
Selection
The Mohr-Coulomb constitutive model is revised to a
combined model with a power law relationship,
comprising both a nonlinear elastic model and an
elastoplastic model. Due to its capability to
synchronize the elastic modulus during loading or
unloading, it is suitable for numerical simulation
studies of excavation in foundation pits. Therefore,
the soil layer in the computational model is
represented by an isotropic modified Mohr-Coulomb
model. Constitutive models for structures such as
crown beams, retaining piles, concrete supports, and
grid columns utilize isotropic linear elastic models.
For moderately weathered silty sandstone, the
values for density, cohesive strength, friction angle,
and Poisson's ratio are 23.6 kN/m
3
, 80 kPa, 30°, and
0.25, respectively. The elastic, secant, tangent, and
unloading moduli are 250 MPa, 321 MPa, 321 MPa,
and 1607 MPa, respectively. For other material
parameters, refer to Table 2 below.
Table 2: Material parameter value table of numerical model.
Uni
t
Material
γ
(kN/m
3
)
μ
E(MPa)
Crown beam/Concrete
support/Concrete tie
b
ea
C30 25 0.20 30000
Column pile C35 25 0.20 31500
Retaining pile C35(reduction) 25 0.20 13230
Grid column/
Steel connectin
g
bea
m
Q235B 78 0.25 206000
The final established model core zone comprises
23 computational grid groups, 363, 106 elements, and
69, 569 nodes. The lateral and bottom boundary
conditions are set as hinge supports and vertical
displacement constraints, respectively. The West
Parking Building structure is simplified based on
zoning, and uniformly distributed surface loads are
applied at corresponding positions in the model.
Figure 6 illustrates a detailed view of the calculation
model for the T3 station magnetic levitation pit.
Figure 6: Details of foundation pit calculation model of
Maglev T3 station.
4.3 Calculation Results and Analysis
Figure 7 illustrates vertical displacement contour
maps of the ground and support structures under
Conditions 1 and 2. After the excavation of the soil in
ICESCE 2024 - The International Conference on Environmental Science and Civil Engineering
274
the magnetic levitation deep pit, the bottom soil
experiences a certain degree of rebound due to the
removal of soil loads, while the surrounding soil
layers of the West Parking Building pit undergo
settlement under the combined effects of construction
loads and soil deformation. A comparison between
Conditions 1 and 2 reveals that the impact of close-
proximity construction on the rebound of the bottom
soil in the magnetic levitation deep pit is minimal.
However, it significantly affects the ground
settlement in West 2 Zone, leading to a slightly
increased settlement of the soil on the south side of
the magnetic levitation deep pit. This shift changes
the focus of settlement from the north side to the south
side in the vicinity of the magnetic levitation deep pit.
Figure 8 shows the horizontal displacement
contour maps of the ground and support structures
under Conditions 1 and 2. After the excavation of the
magnetic levitation deep pit, the horizontal
displacement of the surrounding ground in the Y
direction (north-south) primarily involves the inward
movement of the soil on both sides of the pit. The
maximum deformation is concentrated in the middle
lower part of the retaining piles, with relatively larger
values occurring at locations where there are
significant changes in pit elevation. Comparing
Conditions 1 and 2, close-proximity construction
increases the horizontal displacement of the ground
toward the interior of the magnetic levitation deep pit,
with minimal impact on the form and characteristics
of the ground's horizontal displacement.
Figure 9 presents the deformation contour map of
the retaining piles under Conditions 1 and 2 (enlarged
1500 times to highlight deformation characteristics).
Under the combined action of soil and water pressure,
the retaining piles deform inward towards the
magnetic levitation deep pit, with the maximum
deformation concentrated in the middle lower part
(specifically, 68m above the bottom of the pit).
Comparing Conditions 1 and 2, close-proximity
construction shifts the entire southside retaining pile
parallel to the north side while increasing the
deformation differences between different parts.
However, the load from West 2 Zone has a relatively
small impact on the deformation of the northside
retaining pile.
Figure 10 displays the bending moment contour
map of the retaining piles under Conditions 1 and 2.
The maximum bending moments for the retaining
piles on the north and south sides of the magnetic
levitation deep pit occur at the bottom of the pit.
Comparing Conditions 1 and 2, close-proximity
construction mainly increases the maximum bending
moments of the retaining piles, with a greater increase
on the south side.
Figure 11 illustrates the axial force contour map
of the internal supports under Conditions 1 and 2.
After the excavation of the magnetic levitation deep
pit, both the concrete and steel support experience
axial pressure, with the 112 axis of the concrete
support receiving a higher axial pressure than other
locations. Comparing Conditions 1 and 2, close-
proximity construction increases the axial pressure on
both the concrete and steel supports.
Figure 7: Vertical displacement cloud map of stratum and
supporting structure under different working conditions (a)
Operating condition 1; (b) Operating condition 2.
Feasibility Simulation Analysis of Close-Proximity Construction of Underground Maglev Deep Foundation Pits Under Construction
275
Figure 8: Horizontal displacement cloud map of stratum
and support structure under different working conditions (a)
Operating condition 1; (b) Operating condition 2.
Figure 9: Deformation cloud map of envelope pile under
different working conditions (1500 times larger than actual
deformation) (a) Operating condition 1; (b) Operating
condition 2.
Figure 10: Cloud image of bending moment of retaining
pile under different working conditions (a) Operating
condition 1; (b) Operating condition 2.
Figure 11: Axial force cloud diagram of internal support
(concrete support, steel support) under different working
conditions (a) Operating condition 1; (b) Operating
condition 2.
Quantitative analysis was performed on the
computed results extracted from different axial
regions of the magnetic levitation deep pit under
various conditions, comparing displacements with the
original design requirements as shown in Figure 12.
From Figure 12, it is observed that after applying the
ICESCE 2024 - The International Conference on Environmental Science and Civil Engineering
276
West Parking Building load (Condition 2), the
maximum horizontal, vertical, and deepseated
displacements of the retaining pile head, as well as the
maximum settlement of the surrounding ground, are
all within the original design requirements. The safety
calculations for various indicators in the optimized
deployment plan have passed, and the displacement
increments in Condition 2 relative to Condition 1 are
relatively small. In summary, under the current
conditions, directly constructing the West Parking
Building (with varying construction levels in
different zones) does not compromise the structural
safety of the magnetic levitation deep pit.
Figure 12: Comparison of displacement between different
axis areas and original design requirements.
4.4 Construction Proposal
Although the simulation analysis indicates that the
use of the close-proximity construction approach has
minimal impact on the structural integrity of the
magnetic levitation deep pit, it is imperative to
implement appropriate safety measures to ensure the
project's safety:
(1) Strengthen pit monitoring: Enhance surface
inspections, particularly during the rainy season,
with a focus on crack observations; Timely
collect and compile monitoring data. Report any
alarming values promptly to relevant authorities
for immediate action.
(2) Ensure geological verification: Report any
inconsistencies with survey information
promptly to ensure comprehensive information
management throughout the project.
(3) Develop emergency response plans: Equip
emergency personnel, tools, and materials;
Develop contingency plans for scenarios such as
bottom pressure reversal and the need for
additional anchors or steel supports.
(4) Minimize loadings at intersections: Strictly
prohibit overloading and excessive stacking
phenomena, especially in areas designated for
ridesharing vehicles and social buses.
(5) Provide risk alerts: In case of a sudden increase
in loads during actual construction, immediately
cease operations and notify relevant authorities
for reassessment.
5 RESULT OF FIELD
IMPLEMENTATION
In February 2022, prior to onsite construction
following the optimized deployment plan,
displacement, stress, and water level monitoring
sensors were installed in the magnetic levitation deep
pit. Data were collected at daily intervals. To validate
the applicability of numerical analysis in construction
deployment optimization, monitoring data from the
adjacent section of the magnetic levitation deep pit
and West Parking Building were compared with
numerical simulation results. Due to space limitations,
the analysis focuses on the monitoring data of the
settlement point with the highest average relative
error with numerical simulation results (identified as
CFDB0352). The layout of the settlement monitoring
points is illustrated in Figure 13.
Figure 13: Schematic diagram of settlement monitoring
point layout.
1234
0
3
30
35
40
45
50
4- Maximum ground settlement around the foundation pit
3- Maximum vertical displacement of support pile top
2- Maximum deep horizontal displacement of support piles
Working condition 1 Working condition 2
Original design requirements
Maximum increment of condition 2 relative to condition 1
Computational Object
Displacement
/mm
-0.5
0.0
0.5
1.0
1.5
2.0
Increment
/mm
1- Maximum horizontal displacement in the Y direction of the support pile top
Support pile Maglev foundation pit
West parking building
foundation pit
CF-DB035-2
15m
Settlement monitoring points
Feasibility Simulation Analysis of Close-Proximity Construction of Underground Maglev Deep Foundation Pits Under Construction
277
Figure 14: Comparison between onsite monitoring data and numerical simulation results of settlement monitoring points.
Figure 14 depicts the comparison curve between
the actual measured data and numerical simulation
results for the monitoring point labeled CFDB0352.
As shown in the onsite monitoring data in Figure 14,
the settlement value at the monitoring point
continuously increased after the optimized
deployment construction began, stabilizing after the
completion of the magnetic levitation deep pit's
negative second floor structure. The average relative
error between the numerical simulation results and
onsite monitoring data is 11.69%. The numerical
simulation results are slightly lower than the onsite
monitoring data, attributed to insufficient
consideration of factors such as upper running
vehicles and backfill loads during the numerical
simulation.
6 CONCLUSION
This study employs dynamic management thinking
and finite element analysis to simulate the feasibility
of a proximity construction plan for an in-progress
underground maglev deep excavation. The on-site
implementation validates the safety of the plan.
Results indicate that, under favorable geological
conditions, robust excavation support measures, and
an appropriate proximity distance, the construction
near the maglev deep excavation poses no threat to
structural safety. This application case effectively
avoids the "nesting" phenomenon, offering valuable
insights for similar construction feasibility analyses.
REFERENCES
Ming H. 2023. Strategies and Techniques of Life Cycle–
Embodied Carbon Reduction from the Building and
Construction Sector: A Review. Journal of
Architectural Engineering, 29(3).
Vasilkin A. 2018. Possibilities of applying structural
optimization in building structures computer-aided
design systems. MATEC Web of Conferences, 251, 03-
017.
Gao X, Xu X, Chen Q, et al. 2023. Research on Multi-
objective Optimization Design Method of LID Facility
Layout Scheme in Cold Land City. Journal of Research
in Science and Engineering, 5(9).
A I T, V A G. 2021. Increasing the economic efficiency of
design and construction solutions due to the
automated identification of construction works and
structural elements of information models. IOP
Conference Series: Materials Science and Engineering,
1083(1): 012-076.
Zhan S, Qi L, Yu Z, et al. 2021. Analysis on the Influence
of Shaft and Cross Passage Turn to the Main Line of
Ingate under Different Construction Schemes.
Advances in Civil Engineering, 2021.
Yu C, Meng Z, Lu J, et al. 2019. Feasibility analysis and
research on replacing steel support with deep
foundation pit anchor system. Construction Technology,
48(S1): 201-3.
Ma L, Han C, Li Z, et al. 2022. Design and Feasibility
Analysis of Hydrogen Water Reverse Transportation
System Engineering. Journal of Power Engineering,
42(11): 1024-32.
Cui G, Huang Y, Chang Z, et al. 2022. Feasibility analysis
of TBM application in the construction of the Yajiageng
tunnel's horizontal guide. Construction Technology
(Chinese and English), 51(02): 102-105.
Chen Y, Wang H, Lv T, et al. 2020. Application of BIM
Technology in the Construction Phase of Changsha
Wanjiali Power Shield Tunnel Project [C]//Civil
Engineering Graphics Branch of the China Graphics
Society. 7th International BIM Technology Exchange
Conference-Collection of Papers on Intelligent
Construction and Innovative Development of Building
Industrialization. China Construction Fifth Bureau
Civil Engineering Co., Ltd.
Hua K, Guo H, Li K, et al. 2020. Optimized Selection of
Construction Scheme for Huiqing Expressway
Tunnel. IOP Conference Series: Materials Science and
Engineering, 741012092.
21/11/30
21/12/30
22/01/30
22/02/28
22/03/28
22/04/28
22/05/28
22/06/28
22/07/28
22/08/28
22/09/28
22/10/28
22/11/28
22/12/28
23/01/28
23/02/28
23/03/28
23/04/28
23/05/28
23/06/28
23/07/28
23/08/28
23/09/28
23/10/28
23/11/28
-16
-12
-8
-4
0
2023/01/08
Capping of Maglev Foundation Pit Structure
2022/12/17
Completion of the negative second floor structure
of the maglev foundation pit
settlement/mm
On site monitoring data
Numerical calculation results
2022/06/09
Convene an expert discussion meeting
Optimization deployment construction begins
ICESCE 2024 - The International Conference on Environmental Science and Civil Engineering
278