3.2.3 Fine Perfusion Speed Control
Initial low speed perfusion: When the concrete liquid
surface first contacts the steel cage, the perfusion
speed should be slowed down to reduce the direct
impact force of concrete on the steel cage and avoid
the buoyancy surge resulting in floating.
Speed in stages: reinforced concrete initial setting at
the bottom of the cage, form a stable support, can be
gradually to speed up the infusion speed, to improve
construction efficiency, and ensure the safety of the
infusion process under control.
3.3 Pile Bearing Capacity Control
Technology
3.3.1 Selection of Grouting Mode
In the reinforcement of pile foundation, post-grouting
technology becomes the key because of the high
sensitivity of pile end to sediment (Guang-Yao et al.,
2012). The technology not only strengthens the pile
end sediment and produces bottom expanding effect,
but also the reinforcement effect of the pile end
sediment and soil is much stronger than that of the
pile side mud. Therefore, pile end reinforcement
should be taken as the primary consideration.
According to the Technical code for building pile
foundations (JGJ94-2008), when a single pile end is
grouting, the vertical reinforcement section is set to
be 12 meters above the pile end, which is essentially
focused pile end reinforcement. However, further
analysis shows that if this range is extended to the pile
side area 12 meters above the pile end, the overall
reinforcement effect will be more significant by using
the higher side friction resistance of deep soil.
Therefore, the optimal strategy is to adopt the
combination of pile end and pile side to maximize the
bearing capacity and stability of pile foundation.
3.3.2 Strengthening Mechanism of Post-
Grouting on Pile Side Resistance
In the construction technology of traditional bored
pile, mud wall protection, as a key measure in the
process of hole formation, effectively guarantees the
stability of hole wall and construction safety.
However, the mud crust formed by the gradual
solidification of mud around the hole wall is difficult
to be completely removed in the subsequent concrete
pouring process, thus building a "barrier" between the
pile and the soil. This layer of mud not only changes
the physical properties of pile soil interface, but also
profoundly affects the lateral resistance of pile. The
moisture rich in the mud skin softens the structure of
the adjacent soil under the action of infiltration,
resulting in a significant reduction in the strength of
the soil. At the same time, the mud skin itself has a
lower friction coefficient than the undisturbed soil,
which acts as a "lubricant" between the pile and the
soil virtually, reducing the direct friction contact area
between the pile and the soil, and thus weakening the
generation of pile side friction resistance. In addition,
with the gradual consolidation and hardening of pile
concrete, the mud layer tends to shrink in volume to
varying degrees, which further intensifies the
separation tendency between pile and soil, forming
new micro gaps, and further weakening pile side
resistance (Jia et al., 2011).
At the top of the pile under load, the effect of pile
side grouting can be analogy in around pile to form
an enhanced concentric cylindrical "reinforcing
tape". Through the infiltration and solidification of
the grouting material, the reinforcement belt realizes
the strengthening and integration of the soil on the
side of the pile, and its influence scope extends
roughly to 6 to 10 times the pile diameter. This
expanding effect not only enhances the interaction of
pile-soil interface, but also significantly changes the
stress distribution in soil body. With the formation of
the grouting reinforcement belt, the possible stress
concentration in the soil is relieved, and the shear
stress gradually dissipates and tends to be evenly
distributed within the reinforcement belt. At the outer
edge of the reinforced belt, the shear stress gradually
decreases until it reaches a level close to zero.
4 TECHNOLOGY APPLICATION
In order to test the technical effect, NK0+371.5
Beidong Interworking bridge and LK0+465.3 Xiyang
Interworking bridge of Xiangfen - Quwo - Houma
transit transformation project of National Highway
108 were applied and verified, Figure 5. shows the
installation and welding of the steel cage at the
application site.. The projects are located in Quwo
County, Linfen City, Shanxi Province. The pile body
adopts bored pile. The pile length of Beidong
Interconnecting bridge is 35m, the pile diameter is
1.5m, and the vertical compressive ultimate bearing
capacity of single pile is 16376.04kN. The pile length
of Xiyang interworking bridge is 35m, the pile
diameter is 1.8m, and the designed ultimate bearing
capacity is 13078.73kN.