Description
: Current
: OCR
: OLS Stage 3
: OLS Stage 2
: OLS Stage 1
X-Axis : Current Values
Y-Axis : Relay Working Time
Table 3: OCR and OLS Relay Performance Data.
Working
Current
686,05 744,9 744,9 744,9 1826,97
OCR
T(s)
Calc ~ ~ ~ ~ 4,193
Sim 10000
9999,9 9999,9 9999,9
4,217
OLS
T(s)
Std ~ 5 5,5 6 -
Sim 10000 5 5,5 6 -
OLS
- T1 T2 T3
Condition 0 1 2 3 4
Description
T1 : PMT 20 KV Trafo 2 GI Bangkalan
T2 : PMT 20 KV Trafo 2 GI Sampang, PMT 20
KV Trafo 2 GI Sumenep
T3 : PMT 20 KV Trafo 1 GI Bangkalan,
PMT 20 KV Trafo 1 GI Sampang,
PMT 20 KV Trafo 1 GI Sumenep
0 : Normal
1 : OLS Stage 1
2 : OLS Stage 2
3 : OLS Stage 3
4 : OLS Not Working
The effect of OLS work on the load on Madura Island
is to prevent widespread blackouts due to overloading
by extinguishing some of the load using OLS. The
load that was extinguished based on the data of the
UP2B defense scheme, namely
• At Stage 1, turn off the load. The target of OLS
phase 1 is PMT 20 kV Incoming Transformer-2
150/20 kV GI Bangkalan. The total load that was
extinguished was 18.4 MW.
• Turn off the load at Stage 2. The target of OLS
phase 2 is PMT 20 kV Incoming Transformer-2
150/20 kV GI Sampang and PMT 20 kV Incoming
Transformer-2 150/20 kV GI Sumenep. The total
load that was extinguished was 78 MW.
• Turn off the load at Stage 3. The targets of OLS
phase 3 are PMT 20 kV Incoming Transformer-1
150/20 kV GI Bangkalan, PMT 20 kV Incoming
Transformer-1 150/20 kV GI Sampang, and PMT
20 kV Incoming Transformer-1 150/20 kV GI
Sumenep. The total load that was extinguished
was 81.9 MW.
Table 4: OLS SUTT 150 kV Load Shedding Ujung-
Bangkalan.
Tahap Total Beban (MW)
1 18,4
278
3 81,9
5 CONCLUSION
Based on the results of the analysis and simulation in
this thesis research, it can be concluded:
1. The operation of OCR and OLS relays in terms of
calculations and simulations is in accordance with
the standard calculation provisions regulated by
PLN.
2. The coordination of OLS and OCR relays in
securing the distribution system has gone well,
where OLS works first to secure overload by
using 3 stages. The OLS setting is smaller than the
OCR setting in order to prevent OCR from
working before OLS. OLS stages are
distinguished based on the working time. OLS
works within 5 DT for the first stage, 5.5 DT for
the second stage, and 6 DT for the third stage. And
for OCR working time using standard inverse
characteristics, namely working time based on the
value of the current flowing, the greater the value
of the current flowing, the faster the relay works.
3. OLS works according to the calculation of the
setting value, which is 710 A, but when OLS fails
to reduce the overload, the OCR relay will work,
where the current OCR working setting at Bay
Bangkalan GIS Ujung is 760 A.
OLS has an effect on reducing excessive loads,
namely by extinguishing the load according to the
OLS target to prevent widespread blackouts.
REFERENCES
A. A. S. P. Larekeng, & M. Iqbal. (2020). Analisis kinerja
over current relay (ocr) & ground fault relay (gfr) pada
sistem 20 kv ultg maros menggunanakan alat uji cmc
356.
Anung, & Achirul Ramadhani. (2017). Penerapan ols untuk
meminimalisir pemadaman meluas akibat overload
pada satu penghantar. Jurnal Isu Teknologi, 12(1).
A.W Hidayat. (2013). Analisa Setting Rele Arus Lebih dan
Rele Gangguan Tanah pada Penyulang Topan Gardu
Induk Teluk Betung. Jurnal Rekayasa Dan Teknologi
Elektro, 7(5), 5–28.
E. Pafela, & E. Hamdani. (2016). Studi Penyetelan Relay
Arus Lebih (OCR) Pada Gardu Induk Teluk Lembu