Measurement  of  height  difference  can  be  done 
with  a  flat  slope  measurement  tool,  measuring  the 
height  difference  with  a flat  slope  is  the  process  of 
determining  elevation  or  finding  a  different  height 
between  measured  points  (Masrul  &  Anjasmara, 
2015).  The  role  of  the  survey  is  to  ensure  that  the 
excavation  area  and/or  work  floor  elevation  are 
following  the  plan.  If  the  excavation  has  matched 
with  the  design  elevation  plan,  the  geological  team 
will  check  to  ensure  that  the  excavated  land  as 
compared to the specifications with planning design 
by  the  geological  team,  height  between  measured 
points (Masrul & Anjasmara, 2015). The role of the 
survey  is  to  ensure  that  the  excavation  area  and/or 
work  floor  elevation  are  following  the  plan.  If  the 
excavation  has  matched  with  the  design  elevation 
plan, the geological team will check to ensure that the 
excavated land as compared to the specifications with 
planning design by the geological team. 
  Stake  out  elevation  and  work  floor  marking, 
stake out elevation is to determine the point that 
will be the elevation limit of the work floor plan 
if  the  excavation  of  the  land  has  passed  the 
work  floor  plan  design  (Figure  5).  In  the 
implementation  of  stake  out,  fixing  and 
checking reference points is the first step that 
must be taken (TS-04, 2011). To fix the work 
floor  elevation  limit,  it  can  be  fixed by using 
measurement  tools,  i.e.  a  water  pass,  the 
accuracy of deter- mining the size depends on 
the  tools  used  as  well  as  on  the  accuracy  of 
measurement and what can be executed (Frick 
& Heinz, 1984). After obtaining the work floor 
elevation  limit,  the  work  floor  boundary 
marking is carried out to obtain the work floor 
top  cast.  The  implementation  of  stake  out 
elevation  in  the  field  is  carried  out  using  the 
formula below, i.e: 
Re f Ele(A)WP = Re f Ele(A) + Re f Signs(A)   (1) 
SignsRead(B) = Re f Ele(A)WP–CastTEle(B)   (2) 
 
  The  excavation  situation  was  measured  using 
wa- ter pass and meter. Water pass is used to 
get full cast from the work floor and work floor 
bound-  aries  (Figure  6).  Excavation  situation 
data  is  taken  by  cross  technique  taken  per  1 
meter.  Through  the  measurement  of  the 
excavation  situation,  it  can  be  seen  how  the 
cross-section of excavated land is through the 
results  of  the  profile  lengthwise  and  the 
transverse profile. 
 
 
 
Figure  5:  Stake  out  and  work  floor  elevation  marking 
techniques. 
 
Figure 6: Data retrieval technique for dredging situation. 
The results of this measurement will be processed 
to obtain the volume of work floor casting using the 
cross-section  method  with  the  Mean  Area  equation 
with the following formula (Adi & Aghsatya, 2017): 
 
𝑉
𝐿   (3) 
 
𝑉
𝐿   (4) 
 
Where: 
V
n
  : nth section average volume (m
3
),  
A
1
  : Cross-sectional area 1 (m
2
), 
A
2
  : Cross-sectional area 2 (m
2
), 
L  : Distance between each section (m). 
 
Figure 7  is  the stage of  the wall structure work, 
which  is  the  final  stage  in  developing  the  energy 
reducing construction. Stakeout and marked elevation 
of  the  nth  section  from  wall  design,  Stakeout 
elevation or vertical stakeout is the measurement of 
the main points position and the vertical details of the 
building. The first step is, of course, the determination 
of  the  foundation  elevation  at  a  predetermined 
location  through  the  measurement  of  horizontal 
stakeholder outs. After determining the elevation of 
the  working wall  plan,  estimation of  the  volume  of 
concrete  needed  for  casting  can  be  estimated.  If 
landslides  occur  in the wall  structure area, the  need 
for concrete for  casting  will increase. The  landslide 
result, fillings and/or dental casting are carried out to 
cover  the  landslide  area  so  that  the  initial  concrete 
requirements according to the plan based on the work 
drawings  are  added  to  the  volume  of  the  landslide. 
Calculating volume of the landslide, the survey team 
took  measurements  of  the  situation  of  the landslide 
area, in this measurement using a meter by calculating 
the distance between the structure of the building and 
the area affected by the landslide.