
 
In theory, when CSR level is adjusted from low 
to high, the reactive capacity increases and the 
voltage decreases, vice verse. Three dimensional 
scattering projection diagram 5 is derived from 340 
sets of statistic data. This figure reflects the 
occurrence number of some certain voltage 
difference caused by the change of capacity.  
4.1  Main Impact on Voltage 
When the operating capacity of CSR decreases, most 
of the voltage increases although the amplitude are 
generally small. Nearly 90% of the voltage 
differences are concentrated between 1kV and 6kV. 
Voltage differences reach to 10kV or 20kV also 
occurred, but most are 2kV. When the operating 
capacity increases,most of the voltage decreases. 
Nearly 90% of the voltage drops are concentrated 
between 1kV and 6kV. Voltage drops reach to 10kV 
also occurred, but most are 2kV as well. From above, 
CSR with total capacity of 300Mvar, switching at 
75Mvar of each level, do not significantly affects the 
voltage of 750kV bus, as amplitude of variation 
always within 1%, tending to nominal value. 
Through the analysis of the data, putting the CSR 
into operation and its frequent switching won’t 
influence the operation of 750kV equipment. 
4.2  Analysis of Special Circumstances 
As stated, after the switching of CSR, some voltage 
differences are not within 6kV. Two main classes, 
one is the amplitude of variation bigger than 6kV. 
For example, within the 340 sets of data, voltage 
differences (increase) reach to 20kV appeared twice, 
12kV appeared twice. Voltage differences (decrease) 
reach to 9kV appeared once, 8kV appeared once. 
Although they conform to the theory but are 
different from normal situation. Another is when the 
operating capacity increases, bus voltage also 
increases and when the operating capacity decreases, 
bus voltage also decreases, opposite to the theory, as 
shown in Figure 5 within red circles.  
In the first situation, increasing 20kV for 
example, referring to the nearby switching actions 
and corresponding weather information, wind speed 
changed rapidly at that time so the grid connection 
capacity of wind power is bigger. At 14:29, 
31/03/2012, the operation capacity of CSR dropped 
from 100% to75%, causing voltage increase from 
756kV to 758kV, 2kV increment. Then at 14:38, 
31/03/2012, the operation capacity dropped from 
75% to 50%, causing voltage increase from 758kV 
to 778kV, 20kV increment. This phenomenon 
appears many times within small period furing 340 
sets of data, and always accompanied with large 
amplitude of voltage variation. This phenomenon 
indicates that the primary causes of large amplitude 
of voltage variation after CSR put into operation are 
the big variation of grid connection capacity of wind 
power and lacking of CSR switching capacity within 
one operation time. Introducing short term wind 
power predicting outcomes into control logic of CSR 
is a promising method to solve this problem. 
In the second situation, the variation of voltage 
goes against the theory. Firstly, because all the data 
were recorded manually, so man-made faults won’t 
be eliminated. What’s more, another possibility is if 
wind power changes quite fast, bus voltage 
fluctuated frequently, so during a small period the 
voltage increments or decrements caused by the 
wind power grid connection is bigger than the 
voltage decrements or increments caused by the 
switching of the CSR, so the variation of voltage 
goes against the theory. 
5 CONCLUSIONS 
CSR is the effective means in solving voltage and 
reactive power problems of the power grid caused 
by the large scale wind power integration. This 
thesis combines with the actual operation states of 
300Mvar stepped CSR in Dunhuang 750kV 
substation of China, analyzed its operating 
characteristics, summarized the impact of switching 
actions on bus, the conclusion is as follows: 
(1) 300Mvar CSR is sufficient in solving the voltage 
and reactive power fluctuation problems of the 
power grid of Dunhuang. 
(2) The switching times of CSR is relatively high 
during the period when wind power fluctuates 
frequently. It is suggest that maintenance 
between January and March and strengthened 
inspection of equipment between May and July 
be arranged. 
(3) The thyristor switching of 50% and 75% 
capacity act relative frequently and 25% capacity 
is always put into operation, so they all should be 
treated as emphasis during the maintenance.  
(4) After putting the CSR into operation, the 
variation of bus voltage is limited nearly within 
the acceptable range. That means CSR don’t 
have large impact on bus voltage. 
(5) As wind power changes with large amplitude and 
frequently, large amplitude of voltage variation 
after the variation of CSR capacity may 
occurred. Introducing short term wind power 
SMARTGREENS2013-2ndInternationalConferenceonSmartGridsandGreenITSystems
108