Paper

Paper Unlock

Authors: Akhmal Muammar Dwiki Rafsanjani ; Devi Pratami ; Achmad Fuad Bay and Ageak Raporte Bermano

Affiliation: School of Industrial Engineering, Telkom University, Jl. Telekomunikasi Terusan Buah Batu No.1, Bandung, Indonesia, Indonesia

Keyword(s): Risk, Project Management Maturity Model, Project Risk Management, Construction, Project-Based Organization

Abstract: Construction projects are highly dynamic, but have a lot of risks in every field of work. To reduce the occurrence of a risk to the project, it is obligatory to do project risk management to avoid losses to the project time, cost, and quality. Evaluation of risk management also needs to be done to improve the quality of project risk management. Hence, this research aims to improve project management in one of the project-based organizations in Indonesia by measuring the maturity level of project risk management. This research uses the Project Management Maturity Model (PMMM) as its framework with seven risk management processes as its criteria. This criterion will be used to compile a self-assessment survey that will be disseminated to gather evidence. This research also carried out the weighting and ranking of these criteria using the Analytical Process Hierarchy (AHP) method. The results of this research found that from the results of weighting and ranking that the criteria of prio rity are plan risk management, and the maturity level obtained in the six risk management processes at level 1which is the initial process, and one process at level 4 which is the managed process. Overall, the maturity level of PBO project risk management is currently at level 1, which is the initial process. (More)

CC BY-NC-ND 4.0

Sign In Guest: Register as new SciTePress user now for free.

Sign In SciTePress user: please login.

PDF ImageMy Papers

You are not signed in, therefore limits apply to your IP address 18.226.222.12

In the current month:
Recent papers: 100 available of 100 total
2+ years older papers: 200 available of 200 total

Paper citation in several formats:
Rafsanjani, A.; Pratami, D.; Bay, A. and Bermano, A. (2020). Measurement of Project Risk Management Maturity Level using Project Management Maturity Model (PMMM): Case Research a Telecommunication Company in Indonesia. In Proceedings of the 1st International Conference on Industrial Technology - ICONIT; ISBN 978-989-758-434-3, SciTePress, pages 76-83. DOI: 10.5220/0009405900760083

@conference{iconit20,
author={Akhmal Muammar Dwiki Rafsanjani. and Devi Pratami. and Achmad Fuad Bay. and Ageak Raporte Bermano.},
title={Measurement of Project Risk Management Maturity Level using Project Management Maturity Model (PMMM): Case Research a Telecommunication Company in Indonesia},
booktitle={Proceedings of the 1st International Conference on Industrial Technology - ICONIT},
year={2020},
pages={76-83},
publisher={SciTePress},
organization={INSTICC},
doi={10.5220/0009405900760083},
isbn={978-989-758-434-3},
}

TY - CONF

JO - Proceedings of the 1st International Conference on Industrial Technology - ICONIT
TI - Measurement of Project Risk Management Maturity Level using Project Management Maturity Model (PMMM): Case Research a Telecommunication Company in Indonesia
SN - 978-989-758-434-3
AU - Rafsanjani, A.
AU - Pratami, D.
AU - Bay, A.
AU - Bermano, A.
PY - 2020
SP - 76
EP - 83
DO - 10.5220/0009405900760083
PB - SciTePress